Posted on: September 28, 2023

Word on the Streets

construction vehicles performing roadway subgrade work

September 28, 2023 Update

Next week, as part of our 2020 Street Bond Program, the City’s contractor will be performing sub-grade stabilization on Dawn Drive followed by the placement of a new asphalt surface.  This work is expected to be completed by mid to late October. After Dawn Drive is complete, the contractor will then be mobilizing to Stonybrooke Drive to begin the sub-grade work and asphalt replacement. Nob Hill Drive will round out the Bond Program’s Year 3 Residential Street Projects, and we are striving for completion by mid-December. Residents on impacted streets will be notified via door hangers prior to the work beginning. To prevent project delays, residents are encouraged to move vehicles from the street on days that contractors will be working. For more information about the Street Bond Program, please visit www.nrhtx.com/2020bond

Also, next week, Public Works crews and their contractors will be:

🚧 Making curb, gutter, and subgrade repairs on the following streets in preparation for an upcoming overlay. This work is part of the Preventive Street Maintenance Program. You can find the complete project list and a map at www.nrhtx.com/psm.

  • Central Avenue
  • Chelmsford Place

🚧 Crack sealing asphalt streets as part of the 2023 Preventive Street Maintenance Program. 

For questions, concerns, or additional information, please call the City of North Richland Hills Public Works Street Division at 817-427-6460.


September 21, 2023 Update

The NRH Public Works Traffic Division maintains roughly 8,700 street signs. These signs vary from street name, regulatory, warning, guide, and temporary construction signage. If you see a sign or pole that has been damaged or vandalized, please report it to Public Works at 817-427-6460, or utilize our online form at www.nrhtx.com/reportconcern.

Next week Public Works crews and their contractors will be:

🚧 Continuing work on Stonybrooke Drive, Nob Hill Drive and Dawn Drive. The concrete contractor is finishing up repairs to curbs and gutters, which ensures positive drainage along the street. Next, they will begin sub-grade repairs, followed by placement of the new asphalt pavement. Residents on impacted streets have been notified via door hangers. To prevent project delays, residents are encouraged to move vehicles from the street on days that contractors are working. These projects are part of the 2020 Street Bond Program. For more information, please visit www.nrhtx.com/2020bond.

🚧 Making curb, gutter, and subgrade repairs on Stonecrest Trail and Central Ave in preparation for an upcoming overlay.  This work is part of the Preventive Street Maintenance Program. You can find the complete project list and a map at www.nrhtx.com/psm.

🚧 Crack sealing asphalt streets as part of the 2023 Preventive Street Maintenance Program. 

For questions, concerns, or additional information, please call the City of North Richland Hills Public Works Street Division at 817-427-6460. 


September 14, 2023 Update

Let’s talk streetlights. There are thousands of streetlights in North Richland Hills. The majority, including the streetlights in your neighborhood, are maintained by Oncor. Streetlights located above traffic signals and some along major corridors like Rufe Snow Drive, North Tarrant Parkway and Glenview Drive are maintained by the Public Works Street Division. Currently, there are around 500 streetlights under the city’s maintenance responsibility. If you notice a streetlight that is out, please report it to Oncor at oncorstreetlight.com or 888-313-4747 or to Public Works at www.nrhtx.com/reportconcern or 817-427-6460. If you are unsure who maintains the light, please reach out to Public Works and they will forward it to Oncor if it is their responsibility. 

Next week Public Works crews and their contractors will be:

🚧 Continuing preparations for paving operations on Dawn Drive, Stonybrooke Drive and Nob Hill Drive, which are expected to begin later this month. The concrete contractor is finishing up repairs to curbs and gutters, which ensures positive drainage along the street. Next, they will begin sub-grade repairs, followed by placement of the new asphalt pavement. Residents on impacted streets have been notified via door hangers. To prevent project delays, residents are encouraged to move vehicles from the street on days that contractors are working. These projects are part of the 2020 Street Bond Program. For more information, please visit www.nrhtx.com/2020bond.

🚧 Making curb, gutter, and subgrade repairs on Greenleaf Drive and Stonecrest Trail in preparation for an upcoming overlay.  This work is part of the Preventive Street Maintenance Program. You can find the complete project list and a map at www.nrhtx.com/psm.

🚧 Crack sealing asphalt streets as part of the 2023 Preventive Street Maintenance Program. 

For questions, concerns, or additional information, please call the City of North Richland Hills Public Works Street Division at 817-427-6460. 


September 7, 2023 Update

Next week Public Works crews and their contractors will be:

🚧 Continuing preparations for paving operations on Dawn Drive, Stonybrooke Drive and Nob Hill Drive, which are expected to begin later this month. The concrete contractor is finishing up repairs to curbs and gutters, which ensures positive drainage along the street. Next they will begin sub-grade repairs, followed by placement of the new asphalt pavement. Residents on impacted streets have been notified via door hangers. To prevent project delays, residents are encouraged to move vehicles from the street on days that contractors are working. These projects are part of the 2020 Street Bond Program. For more information, please visit www.nrhtx.com/2020bond.

🚧 Making curb, gutter, and subgrade repairs on Greenleaf Drive and Stonecrest Trail in preparation for an upcoming overlay.  This work is part of the Preventive Street Maintenance Program. You can find the complete project list and a map at www.nrhtx.com/psm.

🚧 Crack sealing asphalt streets as part of the 2023 Preventive Street Maintenance Program. 

For questions, concerns, or additional information, please call the City of North Richland Hills Public Works Street Division at 817-427-6460.


August 31, 2023 Update

Let’s talk about pothole patching. Our crews are out on the road looking, but if you see a pothole please report its location to the Public Works Street Division at 817-427-6460 or online at www.nrhtx.com/reportconcern.

Did You Know?

  • Potholes can be reported year-round, and the Street Division typically makes these repairs within 24 hours of being notified.  
  • A crew is assigned to pothole patching citywide each workday. 
  • In 2022, the Street Division performed:
    • 31,835 square feet of pothole repairs and asphalt level-ups. This equates to 122 square feet per day.
    • 400 tons of asphalt were used, which equates to 1.5 tons per day. 

Also, next week, Public Works crews and their contractors will be:

🚧 Continuing work on Stonybrooke Drive and Nob Hill Drive. A contractor is replacing limited curb and gutter and drive approaches to ensure positive drainage along the street. Once concrete repairs are completed, they will begin the sub-grade repairs, followed by asphalt resurfacing. Residents on impacted streets have been notified via door hangers. To prevent project delays, residents are encouraged to move vehicles from the street on days that contractors will be working. These projects are part of the 2020 Street Bond Program. For more information, please visit www.nrhtx.com/2020bond.

🚧 Making curb, gutter, and subgrade repairs on the following streets in preparation for an upcoming overlay: You can see the complete project list and a map at www.nrhtx.com/psm.

  • Deville Drive
  • Greenleaf Drive

🚧 Crack sealing asphalt streets as part of the 2023 Preventive Street Maintenance Program. 

For questions, concerns, or additional information, please call the City of North Richland Hills Public Works Street Division at 817-427-6460.


Get Alerts on the Go

Stay informed about lane closures and construction updates for the Glenview Drive, Iron Horse Boulevard and Bedford Euless Road reconstruction projects. These projects are part of the 2020 Street Bond Program that is reconstructing 27 NRH streets.

  • Text Glenview to 888777
  • Text Ironhorse to 888777
  • Text Bford to 888777

Helpful Links

Questions?

Please contact the Public Works Street Division at 817-427-6460 or email Public Workswww.nrhtx.com/psm.

Facebook Twitter Email

Other News in City News

containers of oil, gas, cleaning chemicals and paints

Household Hazardous Waste

Posted on: September 27, 2023
Fire Station Open House - October 9-13 from 6pm-8pm

NRHFD Open House

Posted on: September 25, 2023
two young swimmers in water, Pool Safely logo

Grant Award

Posted on: September 19, 2023
Council Chambers.jpg

City Budget & Tax Rate Adopted

Posted on: September 12, 2023
Roadway construction equipment on Iron Horse Blvd

Iron Horse Boulevard Improvements

Posted on: September 8, 2023
water shooting out of ground, with construction equipment in background

Water Main Breaks

Posted on: August 19, 2023
Roadway Asset Services van on street

Citywide Street Assessment

Posted on: August 18, 2023
Nitro Blast

NRH2O New Attraction

Posted on: August 16, 2023
Lane Closed Sign

Glenview Drive Improvements

Posted on: August 14, 2023
road work ahead

Bedford Euless Road Improvements

Posted on: July 21, 2023
seal (web).jpg

FAQs: Backyard Chickens

Posted on: July 26, 2023
Mike Young standing outside City Hall

New Police Chief

Posted on: July 11, 2023
Set of keys laying on pavement

Lost & Found

Posted on: July 6, 2023
Peppa Pig costumed character waving

Peppa Pig Theme Park

Posted on: June 28, 2023
weather station equipment and speaker on light pole at park baseball field

Park Weather Safety

Posted on: June 23, 2023
Large pavilion with picnic tables underneath, surrounded by trees

Park Pavilion

Posted on: June 16, 2023
K9 Luca wearing vest

K-9 Program

Posted on: May 22, 2023
Dispatcher Chelsea Duncan presented certificate of recognition

Special Recognition

Posted on: May 18, 2023
seal (web).jpg

Oaths of Office

Posted on: May 18, 2023
seal (web).jpg

Compliance Court

Posted on: May 11, 2023
Fire Employees recognized

Special Recognition

Posted on: May 11, 2023
shovels

Groundbreaking

Posted on: May 5, 2023
Street Maintenance - slurry seal being placed on asphalt street

Preventive Street Maintenance Program

Posted on: April 25, 2023
Home

Property Value Notices

Posted on: April 19, 2023
70th Anniversary Seal

NRH Celebrates 70th Anniversary

Posted on: March 31, 2023
seal (web).jpg

Annual Comprehensive Financial Report

Posted on: March 21, 2023
water meter and app

New Water Meters

Posted on: February 28, 2023
seal (web).jpg

Charter Review Task Force

Posted on: January 10, 2023
Street icon

2020 Bond Program

Posted on: November 4, 2020
City Point Rendering

City Point Development

Posted on: December 18, 2019