At their Nov. 14, 2022 meeting, the City Council awarded a contract to Bean Electrical Inc. for the construction of the new traffic signal at the intersection of Davis Boulevard and Hightower Drive. The construction timing will be dependent upon the delivery of the signal poles and components. We will share more information as it becomes available.
Dec. 9 Update:
Site work will begin in early 2023, however construction of the signal itself will not occur until summer. Signal poles and components are on order and are expected to arrive by June.